• Baza znanja

GENERAL INFORMATION
(MON-FIR between 6am and 6pm)
+386 1 230 40 03
info@elektro-ljubljana.si

FAILURE NOTICE
(24/7)
+386 1 230 40 02

OTHER CONTACTS

Frequently asked question

What are the costs of acquiring connection approval, a connection contract, metering point acceptance, and connection when the nominal value of main fuse is 3 x 20 A?

Category: Change and new connection approval

The costs of connecting to the electricity distribution network depend on the connected load (network access) and the costs of acceptance and connecting the metering point.

The sum of costs when the nominal value of the main fuse is 3 x 20 A.

New connected load (network access) 484,12 €
Acceptance and connection 121,36 €
Total payment 605,48 €

The investor is obliged to provide the project documentation for the connection and its implementation.

Prices do not include VAT.