What is the cost of disconnecting/reconnecting the metering point on my request?

Category: Disconnection and reconnection

If the metering point owner requests to be disconnected from the distribution network, the costs are EUR 33.54 (VAT included). The costs of a reconnection upon request are the same.

The requirements for reconnection are a signed electricity supply contract, a contract on accessing the distribution network, proof of having paid the connection costs (of EUR 33.54, VAT included, to be shown on request), and a new connection approval if the disconnection occurred over three years ago.